Current Transformer: Learn the Purpose, Cost, and Lead Time to Procure

Current transformer
High accuracy C800 wound current transformer typically used for revenue metering.

Purpose of current transformer

Relays need to know the current magnitude – either for metering or to implement protection schemes. A current transformer (CT) fulfills this role, stepping down hundreds or sometimes thousands of amps to (typically) 5A which is then fed to a relay.

A typical location for CT installation is on the breaker bushing or transformer bushing. These are donut CT’s and use the magnetic field generated by the current (flowing through the bushing) to induce a current in its winding.

Current transformer
Current transformer on a circuit breaker. Image credit: FirstEnergy – Ohio Edison – Lisbon station.

At extra-high-voltage, the circuit breakers are designed as live-tank breakers. Due to the weight and size of CT’s, they cannot be mounted directly on the interrupter housing. External stand-alone CT’s are employed.

External current transformers near live tank breaker
External current transformers near a live tank breaker

For utilities, it is essential to know how much power is imported or exported at its service boundary. A CT, along with a PT, is installed right where the transmission line enters the substation, a demarcation point of ownership.

Current Transformer: Learn the Purpose, Cost, and Lead Time to Procure 1
A current transformer near the dead-end structure where a transmission line enters the substation. Image credit: Western Area Power – Test track substation.

The image below shows a CT mounted on a piece of medium-voltage bus.

External current transformer used near a switch
External current transformer used near a switch

Thus far, you’ve seen stand-alone and donut CTs. Take a look at the bar-type CT and Rogowski coil.

From protection and control stand-point, CT’s establish a zone of protection in the power system. A oneline taken from one of the PEguru ebooks is shown below. It shows how the CT’s on a breaker and a transformer are strategically chosen to implement line protection, transformer protection, and breaker protection.

Substation oneline drawing
Relay oneline for a ring bus substation.

Cost of current transformer

  • 138kV wound stand-alone CT: ~$15,000 /phase
  • 345kV 3000:5A MR C800 accuracy CT: ~$30,000 /phase

Lead time to procure current transformer

Extra high voltage stand-alone unit: ~1 year

Information on cost and lead time is for your general knowledge only. Contact vendor with your equipment specifications for actual figures.

Learn details of other major equipment
OR
Attempt the quiz
/7
Current Transformer: Learn the Purpose, Cost, and Lead Time to Procure 2

Substation Major Equipment

It's simple, let's begin.

What's the purpose of a conventional power transformer?
Question Image
You are building an interconnect station, tying wind farm generation to the power grid. At the substation, the sources are tied through a tie-breaker. Which device would you install to make sure the sources are synchronized?
Question Image
An industrial facility is plagued with voltage flicker (due to harmonics) and poor power factor at the service entrance. Which device would you install to fix both issues?
Question Image
For which event should a surge arrester operate? Check all that apply.
Question Image
A transformer develops an internal fault. Which device would you install on the transformer high-side to interrupt fault current?
Question Image
Which combination of devices would you use to implement power line carrier?
Question Image
In a distribution substation, the available ground-fault current on the low side of the step-down transformer is excessive, over-dutying the switching equipment. What is your cost-effective solution to reducing the fault current?
Question Image

Your score is

The average score is 42%

0%

1 thought on “Current Transformer: Learn the Purpose, Cost, and Lead Time to Procure”

  1. Good morning,What criteria must be taken into account to select CT in HV capacitor banks,especially neutral CT considering the transients

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top